Sunday, 8 December 2013

Main deck and staging construction

Raisers and more raisers.

Now that I have decided that the LED lighting is not going to be bright enough for the layout and the only option is Fluro's, I now need to source enough fluro's to complete the layout.
As this is going to take a week or so, I decided that I would make a start on the main decks at North Creek and Plattsburgh and also the staging for the North and South ends.

Earlier this week I completed all the raisers at North Creek and Plattsburgh. Both of these towns dont have staging tracks below them so I knew I could make a start. During the week I completed the raisers and then today I completed the main decks at both towns as well as the majority of the deck for the North and South staging.. Now to complete the road beds from staging to the main deck of the layout some 300mm higher than staging.

Here are a few progress pictures.
 
Plattsburgh
 
Plattsburgh on the right and North Creek on the left
 
North Creek
 
North Creek from the other end
 
The end of North Staging
 

North Staging
 
North Staging
 
North Staging
 
Plattsburgh from the other end
 
Raisers ready for Willsboro (after I add the deck for the staging line below it)
 
South Staging
 
South staging
 
 South staging
 
 
Thanks for visiting.

1 comment:

  1. It's looking great, Brendan. And you're making very fast progress.

    Regards,
    Ron

    ReplyDelete